Update on recent work at the Rialto

Here is a summary of recent completed or ongoing work (all funded through BEIC unless otherwise noted).

  • Concession Stand: Fully built, stained, and completed
  • Doors: Front and side doors have been restored
  • Interior Carpentry/Painting: Baseboards, crown molding, stairwells, and walls repaired and painted
  • Plumbing: Leak repaired, wall framing and wallpapering in restrooms underway
  • Electrical: 90% completed, including updates to previously incomplete or incorrect work
  • Lighting: Installation of auditorium sconces has begun
  • Flooring: Carpet companies have submitted measurements and bids
  • Curtains: Measurements taken for the lobby and auditorium
  • HVAC: Four experienced companies have assessed the systems; repairs and tests are ongoing
  • Fire Suppression: Water flow test completed. FSC selected, pending city permit due to fire marshal vacancy
  • Seating: Original seats available for sale to raise funds
  • Exterior Work: Four stucco/paint quotes reviewed; contractor selected
  • Marquee Neon & Letters: One company has inspected the sign; a quote for historical letters has been received